Every procedure for foreign investors in Vietnam, in one table

39 procedures from market access to periodic reporting: who decides, who applies, the documents, what must come first, and the legal basis where it is settled. Filter by stage or by entry route.

39 of 39 procedures

  1. Pre-entryMarket accessRequired
    Applicable route
    All routes
    Key question
    Is the sector open to foreign investors, and on what conditions?
    Procedure or approval
    Market-access analysis (no filing)
    Applicant
    Investor / counsel
    Main documents
    Business description; group chart
    Pre-condition
    None
    Must be complete before
    Any filing or signing
    Risk and notes
    Drives structure, ownership and partner choice.
    Statutory timeline
    Confirm with counsel
  2. Pre-entryEntry modeRequired
    Applicable route
    All routes
    Key question
    New company, acquisition, project purchase, BCC, PPP or branch / RO?
    Procedure or approval
    Structuring decision
    Applicant
    Investor / counsel
    Pre-condition
    Market access
    Must be complete before
    Filing
    Risk and notes
    See MASTER DECISION TREE.
    Statutory timeline
    Confirm with counsel
  3. Pre-entryOwnership chainPotentially Required
    Applicable route
    R9 (R9)
    Key question
    Is the investing entity treated as a foreign investor?
    Procedure or approval
    Ownership-chain analysis
    Applicant
    Investor / counsel
    Main documents
    Group chart; registers
    Pre-condition
    None
    Must be complete before
    Filing
    Risk and notes
    Threshold and tiering (confirm with counsel).
    Statutory timeline
    Confirm with counsel
  4. Pre-entryDue diligenceRequired
    Applicable route
    R5, R6, R7 (R5, R6, R7)
    Key question
    What is being bought and what liabilities come with it?
    Procedure or approval
    Legal due diligence
    Applicant
    Investor
    Main documents
    Data room
    Pre-condition
    NDA
    Must be complete before
    Signing
    Risk and notes
    Include licences, land, IRCs held, data and employment.
    Statutory timeline
    Confirm with counsel
  5. Pre-entrySensitive land / national securityCase-Specific Review
    Applicable route
    R3, R6, R7 (R3, R6, R7)
    Key question
    Does the target or project have land in an island, border, coastal or security-sensitive area?
    Procedure or approval
    Screening
    Applicant
    Investor / counsel
    Main documents
    Land-use right certificates
    Pre-condition
    None
    Must be complete before
    Signing
    Risk and notes
    Triggers M&A registration and security consultation.
    Statutory timeline
    Confirm with counsel
  6. Pre-entryMerger controlPotentially Required
    Applicable route
    R5, R6, R7 (R5, R6, R7)
    Key question
    Do the parties meet notification thresholds?
    Procedure or approval
    Economic concentration notification
    Authority
    National Competition Commission
    Applicant
    Parties
    Main documents
    Notification dossier
    Pre-condition
    Signed or agreed deal
    Must be complete before
    Closing
    Risk and notes
    Thresholds (confirm with counsel).
    Statutory timeline
    Confirm with counsel
  7. Investment approvalsInvestment Policy ApprovalCase-Specific Review
    Applicable route
    R2, R3, R8 (R2, R3, R8)
    Key question
    Is the project in an approval category?
    Procedure or approval
    Investment Policy Approval
    Authority
    National Assembly / Prime Minister / Provincial People's Committee (confirm with counsel).
    Applicant
    Investor
    Main documents
    Project proposal; investor documents; land-use need; environmental information
    Pre-condition
    Market access
    Must be complete before
    IRC
    Risk and notes
    Separate from IRC and ERC.
    Statutory timeline
    Confirm with counsel
  8. Investment approvalsInvestor selectionPotentially Required
    Applicable route
    R3, R10 (R3, R10)
    Key question
    Must the investor be chosen by auction or bidding?
    Procedure or approval
    Auction / bidding / investor approval
    Authority
    Provincial authorities; bid-inviting party
    Applicant
    Investor
    Main documents
    Eligibility and bid documents
    Pre-condition
    Investment policy decision
    Must be complete before
    Land allocation / lease
    Legal basis
    Investment Law 143/2025/QH15, Art. 23
    Risk and notes
    State land does not by itself mean auction or bidding. The investor may also be approved together with the investment policy.
    Statutory timeline
    Confirm with counsel
  9. Investment approvalsIRCRequired
    Applicable route
    R1, R2, R3, R4, R8; R9 if foreign-investor treatment (R1, R2, R3, R4, R8, R9)
    Key question
    Does the foreign investor's project need registration?
    Procedure or approval
    Investment Registration Certificate
    Authority
    Investment registration authority
    Applicant
    Investor
    Main documents
    Application; project proposal; legalised investor documents; financial capacity; site documents
    Pre-condition
    Market access; approval where required
    Must be complete before
    Project implementation
    Legal basis
    Investment Law 143/2025/QH15; Decree 96/2026/NĐ-CP
    Risk and notes
    IRC = project registered. Not a licence to operate.
    Statutory timeline
    Confirm with counsel
  10. Investment approvalsSpecial investment procedurePotentially Required
    Applicable route
    R4 (R4)
    Key question
    Is the project in an eligible zone and outside the excluded project categories?
    Procedure or approval
    Special-procedure registration with undertakings (investor's option)
    Authority
    Zone Management Board (confirm with counsel).
    Applicant
    Investor
    Main documents
    Application; written undertakings
    Pre-condition
    Eligible zone; not an excluded category
    Must be complete before
    Construction
    Legal basis
    Investment Law 143/2025/QH15, Art. 28; Decree 96/2026/NĐ-CP
    Risk and notes
    No separate Investment Policy Approval, technology appraisal, EIA report, detailed planning, construction permit and certain construction / fire approvals. Standards still apply; post-inspection.
    Statutory timeline
    Confirm with counsel
  11. Investment approvalsM&A registrationCase-Specific Review
    Applicable route
    R6 (not R5) (R6)
    Key question
    Conditional sector AND an increase in total foreign ownership? Crossing / increasing above 50%? Sensitive land?
    Procedure or approval
    Registration of capital contribution / share purchase by foreign investor
    Authority
    Investment registration authority
    Applicant
    Foreign investor
    Main documents
    Registration form; investor documents; agreement in principle; target documents
    Pre-condition
    Trigger analysis (Questionnaire Q12, Q13, Q17, L1)
    Must be complete before
    Closing / payment
    Legal basis
    Investment Law 143/2025/QH15, Art. 21(3)
    Risk and notes
    Not an IRC. A conditional sector alone is not a trigger: foreign-to-foreign sales that leave total foreign ownership unchanged stay on R5.
    Statutory timeline
    Confirm with counsel
  12. Investment approvalsPublic / listed TargetPotentially Required
    Applicable route
    R5, R6 (Track B) (R5, R6)
    Key question
    Is the Target a public or listed company?
    Procedure or approval
    Foreign ownership room; trading code; tender offer; disclosure
    Authority
    State Securities Commission; stock exchange; depository
    Applicant
    Foreign investor; Target
    Main documents
    Trading code dossier; tender offer file; disclosure forms
    Must be complete before
    Purchase of shares
    Risk and notes
    Runs in addition to the investment-law test.
    Statutory timeline
    Confirm with counsel
  13. Investment approvalsSector regulator approval of acquisitionPotentially Required
    Applicable route
    R5, R6, R7 (R5, R6, R7)
    Key question
    Does sector law require approval of the new owner?
    Procedure or approval
    Approval of change of owner / major shareholder
    Authority
    State Bank; Ministry of Finance; other sector regulators
    Applicant
    Target / investor
    Main documents
    Per sector
    Must be complete before
    Closing
    Risk and notes
    Banking, insurance, securities and others.
    Statutory timeline
    Confirm with counsel
  14. Investment approvalsState capitalPotentially Required
    Applicable route
    R5, R6 (R5, R6)
    Key question
    Is the seller the State or a State-owned enterprise?
    Procedure or approval
    State-capital transfer procedure (valuation, auction, approval)
    Authority
    Owner's representative agency
    Applicant
    Seller
    Main documents
    Valuation; approval decision
    Must be complete before
    Signing
    Risk and notes
    Governs how the seller may sell.
    Statutory timeline
    Confirm with counsel
  15. Investment approvalsProject transferPotentially Required
    Applicable route
    R7 (R7)
    Key question
    Does the transfer need approval / IRC adjustment?
    Procedure or approval
    Adjustment of approval / IRC
    Authority
    Investment registration authority; approving authority
    Applicant
    Transferor and transferee
    Main documents
    Transfer agreement; transferee documents; project report
    Pre-condition
    Eligibility of project and transferee
    Must be complete before
    Land / asset transfer
    Statutory timeline
    Confirm with counsel
  16. Investment approvalsPPP approvalsRequired
    Applicable route
    R10 (R10)
    Key question
    What approvals apply under the PPP Law?
    Procedure or approval
    PPP investment policy decision; project approval; investor selection
    Authority
    Competent authority under PPP Law
    Applicant
    Contracting authority / investor
    Main documents
    Pre-FS; FS; bid
    Pre-condition
    Project identification
    Must be complete before
    PPP contract
    Risk and notes
    IRC interaction (confirm with counsel).
    Statutory timeline
    Confirm with counsel
  17. Corporate registrationERCRequired
    Applicable route
    R1, R2, R3, R4, R9, R10; R7 if new vehicle (R1, R2, R3, R4, R7, R9, R10)
    Key question
    Is a new Vietnam company being created?
    Procedure or approval
    Enterprise Registration Certificate
    Authority
    Business Registration Office
    Applicant
    Investor / founders
    Main documents
    Application; charter; member list; legalised investor documents; beneficial owner information
    Pre-condition
    IRC (or ERC-first where available)
    Must be complete before
    Opening bank accounts; contracting
    Risk and notes
    ERC = company exists. Not permission to commence regulated business.
    Statutory timeline
    Confirm with counsel
  18. Corporate registrationCorporate changes after M&ARequired
    Applicable route
    R5, R6 (R5, R6)
    Key question
    Have the new owners been registered?
    Procedure or approval
    Change of members / shareholders; ERC amendment
    Authority
    Business Registration Office
    Applicant
    Target company
    Main documents
    Transfer documents; M&A approval (R6)
    Pre-condition
    Closing
    Must be complete before
    Exercising rights with third parties
    Statutory timeline
    Confirm with counsel
  19. Corporate registrationBeneficial owner informationRequired
    Applicable route
    All company routes
    Key question
    Has beneficial ownership been identified and filed?
    Procedure or approval
    Beneficial owner declaration
    Authority
    Business Registration Office
    Applicant
    Company
    Main documents
    Beneficial owner list
    Must be complete before
    ERC / change filing
    Risk and notes
    Rules introduced 2025; amended 2026 (confirm with counsel).
    Statutory timeline
    Confirm with counsel
  20. Corporate registrationBranch / RO licenceRequired
    Applicable route
    Branch / RO
    Key question
    Is a presence without a subsidiary enough?
    Procedure or approval
    RO or branch establishment licence
    Authority
    Department / Ministry of Industry and Trade (confirm with counsel).
    Applicant
    Foreign trader
    Main documents
    Application; legalised parent documents; financials; lease
    Pre-condition
    Parent's operating history
    Must be complete before
    Any activity
    Risk and notes
    RO cannot earn revenue.
    Statutory timeline
    Confirm with counsel
  21. Corporate registrationBCC operating officePotentially Required
    Applicable route
    R8 (R8)
    Key question
    Does the foreign BCC party need an office?
    Procedure or approval
    Operating office registration
    Authority
    Investment registration authority
    Applicant
    Foreign BCC party
    Main documents
    Registration dossier
    Pre-condition
    IRC
    Must be complete before
    Hiring / banking for the BCC
    Statutory timeline
    Confirm with counsel
  22. Capital & bankingCapital accountRequired
    Applicable route
    All except Branch / RO
    Key question
    Which account must receive the investment?
    Procedure or approval
    DICA or indirect investment account
    Authority
    Licensed bank (State Bank rules)
    Applicant
    Company / investor
    Main documents
    ERC; IRC; KYC
    Pre-condition
    ERC
    Must be complete before
    First capital remittance
    Risk and notes
    FX-law test differs from investment-law test.
    Statutory timeline
    Confirm with counsel
  23. Capital & bankingCapital contributionRequired
    Applicable route
    R1-R4, R9, R10 (R1, R2, R3, R4, R9, R10)
    Key question
    Is capital paid in full and on time?
    Procedure or approval
    Contribution within statutory period
    Authority
    Bank; Business Registration Office
    Applicant
    Investor
    Main documents
    Bank credit advices
    Pre-condition
    Capital account
    Must be complete before
    Statutory deadline
    Risk and notes
    Late contribution → capital reduction and penalties.
    Statutory timeline
    Confirm with counsel
  24. Capital & bankingM&A paymentRequired
    Applicable route
    R5, R6, R7 (R5, R6, R7)
    Key question
    Is the purchase price routed correctly?
    Procedure or approval
    Payment via correct account; seller tax filing
    Authority
    Bank; tax authority
    Applicant
    Buyer / seller
    Main documents
    SPA; approval notice (R6)
    Pre-condition
    Approval (R6)
    Must be complete before
    Closing
    Statutory timeline
    Confirm with counsel
  25. Capital & bankingForeign loansPotentially Required
    Applicable route
    All routes
    Key question
    Will the company borrow offshore?
    Procedure or approval
    Foreign loan registration / reporting
    Authority
    State Bank of Vietnam
    Applicant
    Borrower
    Main documents
    Loan agreement; IRC
    Pre-condition
    Signed loan
    Must be complete before
    Drawdown (registered loans)
    Risk and notes
    Borrowing room tied to IRC investment capital.
    Statutory timeline
    Confirm with counsel
  26. Land / premisesRegistered address and premisesRequired
    Applicable route
    All routes
    Key question
    Does the company have a lawful right to use its premises?
    Procedure or approval
    Lease / sublease
    Applicant
    Company
    Main documents
    Lease; landlord title documents
    Must be complete before
    ERC (address); operation (use)
    Risk and notes
    Use must match zoning.
    Statutory timeline
    Confirm with counsel
  27. Land / premisesState land lease / allocationPotentially Required
    Applicable route
    R2, R3, R10 (R2, R3, R10)
    Key question
    Is land obtained from the State?
    Procedure or approval
    Land lease / allocation decision; land-use right certificate
    Authority
    Provincial People's Committee; land authority
    Applicant
    Project company
    Main documents
    Approval; IRC; cadastral file
    Pre-condition
    Approval / selection result
    Must be complete before
    Construction
    Statutory timeline
    Confirm with counsel
  28. Land / premisesZone subleasePotentially Required
    Applicable route
    R1, R2, R4 (R1, R2, R4)
    Key question
    Is the site inside an industrial or other zone?
    Procedure or approval
    Sublease with zone developer
    Authority
    Zone Management Board; developer
    Applicant
    Company
    Main documents
    Sublease; developer's land documents
    Pre-condition
    IRC / ERC
    Must be complete before
    Construction
    Risk and notes
    Check developer's land-rent payment method.
    Statutory timeline
    Confirm with counsel
  29. Construction / environment / fireEnvironmental approvalCase-Specific Review
    Applicable route
    Projects with physical footprint
    Key question
    Does the project need an EIA, environmental licence or registration?
    Procedure or approval
    EIA approval; environmental licence; environmental registration
    Authority
    Environment authority (confirm level with counsel)
    Applicant
    Project owner
    Main documents
    EIA report; licence dossier
    Pre-condition
    Site; design
    Must be complete before
    Construction (EIA); operation (licence)
    Risk and notes
    Categories changed recently (confirm with counsel).
    Statutory timeline
    Confirm with counsel
  30. Construction / environment / fireConstructionPotentially Required
    Applicable route
    Projects with works
    Key question
    Are permits and acceptance needed for the works?
    Procedure or approval
    Design appraisal; construction permit or exemption; completion acceptance
    Authority
    Department of Construction; Zone Management Board
    Applicant
    Project owner
    Main documents
    Design files; land documents
    Pre-condition
    Land; EIA where required
    Must be complete before
    Start of works; use of building
    Risk and notes
    Under R4 the construction permit is not carried out separately; undertakings and post-inspection apply.
    Statutory timeline
    Confirm with counsel
  31. Construction / environment / fireFire safetyPotentially Required
    Applicable route
    Projects with works / fit-out; manufacturing
    Key question
    Are fire-safety design approval and acceptance needed?
    Procedure or approval
    Fire-safety design appraisal; acceptance
    Authority
    Fire police
    Applicant
    Project owner / tenant
    Main documents
    Fire-safety design; as-built file
    Pre-condition
    Design
    Must be complete before
    Use of building
    Risk and notes
    Applies to many fit-outs.
    Statutory timeline
    Confirm with counsel
  32. Sector licencesConditional business linesCase-Specific Review
    Applicable route
    All routes
    Key question
    Does the activity need a licence or to meet conditions?
    Procedure or approval
    Sector-specific licence / certificate
    Authority
    Sector regulator
    Applicant
    Company
    Main documents
    Per sector
    Pre-condition
    ERC; facilities; staff
    Must be complete before
    Starting the regulated activity
    Risk and notes
    ERC business line ≠ licence. Case-specific legal review required.
    Statutory timeline
    Confirm with counsel
  33. Sector licencesTrading / retailPotentially Required
    Applicable route
    All routes
    Key question
    Will the company retail goods or carry out listed trading activities?
    Procedure or approval
    Business Licence; Retail Outlet Licence
    Authority
    Department of Industry and Trade
    Applicant
    Company
    Main documents
    Application; financial plan; outlet documents
    Pre-condition
    ERC / IRC
    Must be complete before
    Retail sales
    Risk and notes
    Economic needs test may apply.
    Statutory timeline
    Confirm with counsel
  34. Tax / employment / complianceTax set-upRequired
    Applicable route
    All company routes
    Key question
    Is the company ready to invoice and file?
    Procedure or approval
    Initial tax registration; e-invoice; accounting regime
    Authority
    Tax authority
    Applicant
    Company
    Main documents
    ERC; digital signature
    Pre-condition
    ERC; bank account
    Must be complete before
    First invoice
    Statutory timeline
    Confirm with counsel
  35. Tax / employment / complianceEmployment set-upRequired
    Applicable route
    All routes
    Key question
    Are contracts, insurance and internal rules in place?
    Procedure or approval
    Labour declaration; social insurance registration; internal labour rules
    Authority
    Labour authority; Vietnam Social Security
    Applicant
    Company
    Main documents
    Contracts; payroll list
    Pre-condition
    ERC
    Must be complete before
    First payroll
    Statutory timeline
    Confirm with counsel
  36. Tax / employment / complianceForeign staffPotentially Required
    Applicable route
    All routes
    Key question
    Do foreign nationals have work authorisation and the right visa?
    Procedure or approval
    Work permit or exemption; visa / residence card
    Authority
    Labour authority; immigration
    Applicant
    Company
    Main documents
    Legalised degrees; experience letters; police and health checks
    Pre-condition
    ERC
    Must be complete before
    First working day
    Risk and notes
    Long lead time for legalisation.
    Statutory timeline
    Confirm with counsel
  37. Tax / employment / compliancePersonal data and cybersecurityRequired
    Applicable route
    All routes
    Key question
    Is personal data processed or sent abroad?
    Procedure or approval
    Data protection compliance; impact assessment dossiers
    Authority
    Ministry of Public Security
    Applicant
    Company
    Main documents
    Processing records; assessments
    Must be complete before
    Start of processing / transfer
    Statutory timeline
    Confirm with counsel
  38. Commercial operationGo-liveRequired
    Applicable route
    All routes
    Key question
    Is every mandatory item complete?
    Procedure or approval
    GO-LIVE CHECKLIST
    Applicant
    Company / counsel
    Pre-condition
    All above
    Must be complete before
    First commercial transaction
    Risk and notes
    Do not rely on ERC / IRC alone.
    Statutory timeline
    Confirm with counsel
  39. Commercial operationOngoing reportingRequired
    Applicable route
    All routes
    Key question
    What must be filed after go-live?
    Procedure or approval
    Investment, tax, labour, statistics and sector reports
    Authority
    Investment registration authority; tax; others
    Applicant
    Company
    Main documents
    Periodic reports
    Must be complete before
    Each deadline
    Risk and notes
    Missed reports are a frequent cause of fines.
    Statutory timeline
    Confirm with counsel

Statutory time limits and some authority names are left for confirmation in the source workbook and are not filled in here. Legal status reviewed as of 18 September 2026.